History

2_2

Efficient operation since 2009

2001

Development of the Ust Luga port begins


2006

Dredging works begin and the site of the terminal is constructed


весна2007_ен

Construction of the terminal is in full swing


осень2007_ен

Construction of railway tracks is completed


весна2008_ен

Assembly of the shiploader begins


лето2008_)ен

The warehouse is constructed and the portal reclaimer is assembled


осень2008-ен

Construction of the wagon unloading station continues


весна2009_ен

Commissioning of the main equipment begins


лето2009_ен

First handling of bulk materials is performed


осень2009_ен

The facility for sulfur handling is put into operation